1st March 2023 Report

  • C- BLOCK – Raft concrete work in progress.
  • D- BLOCK – Basement – 1 Column & share walls Reinforcement in progress.

1st February 2023 Report

  • C- BLOCK – Raft Reinforcement in progress.
  • D- BLOCK – Basement – 2 slab work in progress.

1st January 2023 Report

  • D block 1st slab completed second slab work in progress.
  • C block footing work in progress.