Project Status

CONSTRUCTION UPDATES

October 2024 Report

  • C- BLOCK – 11th Floor Roof Slab Pour -2 Completed.
  • D- BLOCK – 13th Floor Roof Slab Pour-1 Completed.
  • E- BLOCK – 12th Floor Roof Slab Completed.
  • F- BLOCK – 7th Floor Roof Slab Pour-1 Completed.
     

September 2024 Report

  • C- BLOCK – 10th Floor Roof Slab Completed.
  • D- BLOCK – 12th Floor Roof Slab pour-1 Completed.
  • E- BLOCK – 11th Floor Roof Slab  pour-1 Completed.
  • F- BLOCK – 6th Floor Roof Slab Completed.
     

August 2024 Report

  • C- BLOCK – 9th Floor Roof Slab Work In Progress
  • D- BLOCK – 11th Floor Roof Slab Work In Progress.
  • E- BLOCK – 9th Floor Roof Slab Work In Progress.
  • F- BLOCK – 6th Floor Roof Slab Work In Progress.
     

July 2024 Report

  • C- BLOCK –  8th floor roof slab work in progress.
  • D- BLOCK – 10th floor roof slab completed.
  • E- BLOCK – 7th floor roof slab work in progress.
  • F- BLOCK – 4th floor roof slab work in progress.

June 2024 Report

  • C- BLOCK – 05th floor roof slab Reinforcement work in progress.
  • D- BLOCK – 08th Floor roof slab Reinforcement work in progress.
  • E- BLOCK – 04th floor roof slab Reinforcement work in progress.
  • F- BLOCK – 02nd floor roof slab Reinforcement work in progress.

May 2024 Report

  • C- BLOCK – 04th floor roof slab Reinforcement work in progress.
  • D- BLOCK – 07th Floor roof slab Reinforcement work in progress.
  • E- BLOCK – 03rd floor roof slab Reinforcement work in progress.
  • F- BLOCK – 01st floor roof slab shuttering work in progress.

April 2024 Report

  • C- BLOCK – 02nd  floor roof Reinforcement work in progress.
  • D- BLOCK – 06th Floor roof slab work in progress.
  • E- BLOCK – 02nd floor roof Reinforcement work in progress.
  • F- BLOCK – Ground floor roof slab shuttering work in progress.

March 2024 Report

  • C- BLOCK – First floor roof slab pour-1 work in progress, pour-2 completed.
  • D- BLOCK –  5th Floor roof slab work in progress, pour-2 completed.
  • E- BLOCK – First floor roof pour-1 work in progress.
  • F- BLOCK – Ground floor roof pour-1 work in progress.

February 2024 Report

  • C- BLOCK – Ground floor Roof slab completed.
  • D- BLOCK – 5th Floor walls reinforcement work in progress.
  • E- BLOCK – Ground floor walls reinforcement work in progress.
  • F- BLOCK –  Basement- 1 Roof slab work in progress.

January 2024 Report

  • C- BLOCK – Ground floor slab Reinforcement in progress.
  • D- BLOCK – Second floor slab work in progress.
  • E- BLOCK – Basement- 1 slab Reinforcement in progress.
  • F- BLOCK – Basement- 2 roof shuttering in progress.

December 2023 Report

  • C- BLOCK – Ground floor Roof slab work in progress.
  • D- BLOCK – 3rd floor roof slab work in progress.
  • E- BLOCK – Basement- 1 Roof slab work in progress.
  • F- BLOCK – Basement- 1 Roof slab work in progress.

November 2023 Report

  • C- BLOCK – Basement – 1 roof slab completed.
  • D- BLOCK – First floor roof slab completed.
  • E- BLOCK – Basement- 2 roof slab completed.
  • F- BLOCK – Basement- 2 roof slab completed.

October 2023 Report

  • C- BLOCK – Basement – 1 roof slab concrete work in progress.
  • D- BLOCK – First floor roof slab work in progress.
  • E- BLOCK – Basement- 2 roof slab work in progress.
  • F- BLOCK – Basement- 2 roof slab work in progress.

September 2023 Report

  • C- BLOCK – Basement – 1 roof slab shuttering in progress.
  • D- BLOCK – Ground floor pour-1 completed, Pour- 2 Reinforcement in progress.
  • E- BLOCK – Basement- 3 Pour- 1 completed, Pour- 2 shuttering in progress.
  • F- BLOCK – Basement- 3 Pour- 1 completed, Pour- 2 shuttering in progress.

August 2023 Report

  • C- BLOCK – Basement – 2 slab shuttering work in progress.
  • D- BLOCK – Ground floor wall Reinforcement in progress.
  • E- BLOCK – Basement- 4 slab Pour- 2 shuttering work in progress.
  • F- BLOCK – Basement- 4 slab Pour- 2 shuttering work in progress.

July 2023 Report

  • C- BLOCK – Basement – 2 wall Reinforcement work in progress.
  • D- BLOCK – Ground floor wall Reinforcement in progress.
  • E- BLOCK – Basement- 4 wall concrete work in progress.
  • F- BLOCK – Basement- 4 wall concrete work in progress.

June 2023 Report

  • C- BLOCK – Basement – 3 Roof slab Reinforcement work in progress.
  • D- BLOCK – Basement – 1 (Transfer slab) Pour- 1 completed.
  • E- BLOCK – Raft completed, Basement – 4 wall Reinforcement in progress.
  • F- BLOCK – Raft Reinforcement work in progress.

May 2023 Report

  • C- BLOCK – Basement – 4 Roof slab concrete casting work in progress.
  • D- BLOCK – Basement – 1 (Transfer slab) shuttering work in progress.
  • E- BLOCK – Raft reinforcement work in progress.
  • F- BLOCK – PCC work casting completed, raft work to be started. 

April 2023 Report

  • C- BLOCK – Basement – 4 Roof slab shuttering in progress.
  • D- BLOCK – Basement – 1 (Transfer slab) shuttering in progress.
  • E- BLOCK – Raft reinforcement work in progress.
  • F- BLOCK – Raft PCC work in progress.

March 2023 Report

  • C- BLOCK – Raft concrete work in progress.
  • D- BLOCK – Basement – 1 Column & share walls Reinforcement in progress.

February 2023 Report

  • C- BLOCK – Raft Reinforcement in progress.
  • D- BLOCK – Basement – 2 slab work in progress.

January 2023 Report

  • D block 1st slab completed second slab work in progress.
  • C block footing work in progress.

    This will close in 0 seconds

      This will close in 0 seconds

        This will close in 0 seconds

          This will close in 0 seconds

            This will close in 0 seconds

              This will close in 0 seconds

              Call Now Button